Anticipated Construction Works planned during November 2022:



Despite the adverse weather conditions, the site continues to make significant process with a number of enabling works being progressed and completed this month. Breheny Civil Engineering Ltd are planning to undertake and supervise the following works during this month:
- Commence drainage installation and public footway construction in Harrier Lane
- Continue with drainage installation in Field 2
- Undertake further archaeological excavations in Field 3 near to the Spinney entrance
- Removal of muck away
- Materials delivery