Anticipated Construction Works planned during May 2023:

Breheny Civil Engineering Ltd are planning to undertake and supervise the following works during this month:

  • Management of surface water runoff involving use of water treatment system (dependant on weather conditions).
  • Demolition of disused shed in Field 3 and removal of asbestos contaminated materials (dependant on weather conditions).
  • Complete foul drainage installation in Harrier Lane and remove traffic management.
  • Commence new footway construction in Harrier Lane.
  • Earthworks in Field 2.
  • Drainage in Field 2.
  • Soil muckaway from Field 1.
  • Complete the footpath to the Spinney

If you have any queries about the ongoing works, please contact the Breheny Civil Engineering Site Agent, Mr Harayshan Pirabaharan, on Mob. 07399 528626.