Anticipated Construction Works planned during July 2023:

Breheny Civil Engineering Ltd are planning to undertake and supervise the following works during this month:

  • Management of surface water runoff involving the use of a water treatment system (dependent on weather conditions).
  • Demolition of the disused shed in Field 3 and removal of asbestos-contaminated materials (dependent on weather conditions).
  • Road construction and drainage installation in Fields 2 & 3
  • Soil muckaway from Field 3 via the Spinney.

If you have any queries about the ongoing works, please contact the Breheny Civil Engineering Site Agent, Mr Harayshan Pirabaharan, on Mob. 07399 528626. For any further queries about the housing scheme please contact HousingCompany.Admin@rother.gov.uk