In 2026, Rother District Council (RDC) will have a duty to collect Food Waste as part of our Waste Collection strategy. To accommodate this RDC are leasing the Sidley Depot site from East Sussex County Council (ESCC).

The main purpose of the Sidley Depot site will be a continuation of its former use – as a depot for overnight parking of vehicles, and for daytime parking of staff vehicles whilst staff are on waste collection rounds. Biffa will also use the site for maintenance and repair of some of their fleet of vehicles.

The project will entail the demolition of all existing buildings on site and establishing a new workshop building that will be designed to allow for the repair and maintenance of waste vehicles. The proposed building will include a small area for administrative staff, welfare plus storage.

Aerial image showing the site on Google Maps
An aerial image of the site

Project Timeline

Key MilestonesMilestone Dates
Demolition Consent receivedApril 2025
Demolition of existing buildingsMay 2025
Planning Consent receivedDecember 2025
Decontamination of site February 2026
Planned Construction CommencementFebruary 2026
Minor works on site/Portakabin installationFebruary/March 2026
Biffa food waste service commences31st March 2026
New workshop contractor tenderSpring 2026
New workshop construction startsSummer 2026
Workshop completionSpring 2027

Our new weekly food waste service has begun from the Sidley Depot site. There is a temporary site set up for Biffa whilst we procure a contractor to build the permanent workshop facility.

Permission was granted at December 11th 2025 Planning Committee for the building of a new vehicle maintenance workshop, administrative and welfare buildings, and associated operation equipment and parking allocation.

The report and committee meeting can be viewed online here: Agenda for Planning Committee on Thursday 11th December 2025, 9.30 am – Rother District Council

Contamination contractors will be boring trial holes around the site to identify the extent of any land contamination.

The demolition of all the buildings has been completed!

The removal of asbestos and demolition of all the buildings has commenced.

The PND was approved at Committee – view the decision.

The Prior Notification for Demolition (PND) was submitted to our Planning Team.

Get in touch

If you have any queries about the project, please contact projects@rother.gov.uk.