In 2024, planning was approved for the demolition of the existing football changing block and replacement with a new state-of-the-art community centre with football changing facilities, café and multi-use/function rooms. This project started with the Heart of Sidley Community group; and with the help of RDC, local residents and stakeholders, it will come to fruition in Spring 2026!
See our team working on site in this footage here: Week of 23rd Feb Drone Footage Update
See January Progress pictures here:


















| Key Milestones | Milestone Date |
|---|---|
| Contractor Procurement | August 2024 |
| BMR appointed | January 2025 |
| Completion | May 2026 |
Get in touch
If you have any queries about the project, contact projects@rother.gov.uk.