The CIL Coronavirus Regulations provide the Council with discretion for a limited time to defer CIL payments and disapply late payment interest. This will only apply in certain circumstances and if it is considered appropriate by the Council. The CIL Coronavirus Regulations came into effect on 22nd July 2020 and will remain in effect until 31st July 2021. The measures to defer CIL payments and disapply late payment interest only apply to CIL payments that are payable between 22nd July 2020 and 31st July 2021. This applies to individuals, small and medium sized developers only.

Deferring CIL payments

A developer can request that the Council defer the payment of CIL. A request can be made no more than 14 days before the CIL payment is due.

Requests must be submitted using the CIL Deferral Request Application Form

The developer must:

  • Have an annual turnover of less than £45 million
  • Be experiencing financial difficulties because of the effect of Coronavirus which means they are having difficulty in paying CIL
  • Have a CIL payment which is payable between 22nd July 2020 and 31st July 2021*
    *This can include payments which became due on or after 21st March 2020 and are still outstanding which means payment is required between 22nd July 2020 and 31st July 2021.

CIL Deferral process

  1. The developer can make a request to the Council, in writing, no more than 14 days before or as soon as practicable after the date the CIL payment is due
  2. The Council may request information from the developer to help consider a request. The developer must provide such information, in so far as it is in their possession or control, within 14 days beginning with the day on which the request was made. The Council can refuse to grant a request if the information is not provided within 14 days
  3. The Council must refuse or grant a request within 40 days beginning on the day on which the request is received
  4. If granted, the Council will provide a payment deferral for 6 months, beginning on the day on which the request was received. The Council will issue a Revised CIL Demand Notice to confirm the amount payable and when payment is due

If the deferred payment date falls between 22nd July 2020 and 31st July 2021, the developer can make a further deferral request.  If a further deferral is granted, the new payment date will be 6 months after the original deferred payment date.

Evidence to support a CIL deferral request

With any deferral request, the developer must provide the following:

Any evidence which the Council requests must be provided within 14 days of the request being made. If the requested evidence is not provided, the Council may refuse a deferral request.

For checking annual turnover to confirm whether a developer is eligible, the following conditions apply.

  • The developer is a sole enterprise – it is the turnover of the applicant only which is assessed, as shown in the latest set of accounts
  • The developer is part of a group with partners or linked enterprises – the turnover of the applicant, together with the turnover of any linked enterprises, any partners of any linked enterprises, any enterprises linked to any of the applicant’s partners and any enterprise linked to the applicant’s linked companies will be assessed

Please note: it is the responsibility of the applicant/developer to provide all of the above information. Rother District Council can only consider a payment deferral if all of the above material is supplied and is sufficient.

Refusal of a CIL deferral request

If the Council refuses a deferral request, the developer will have 7 days beginning on the day which the deferral request is refused to make the CIL payment. This includes any late payment interest prior to the deferral request being made.

Right of appeal for a refused CIL deferral request

The CIL Coronavirus Regulations do not provide a right of appeal if a deferral request is refused.

Further information: